Click here to view La Crosse Area Weather
Home > Columnists > Story
 Advertisement 

SECTION SPONSORS


Published - Tuesday, April 22, 2008

POST COMMENT | READ COMMENTS (7 comment(s))

The truth about sewer and water


.
It’s inevitable each time I report on the La Crosse-La Crescent pipeline, someone — a blogger, letter writer or otherwise — misreads, misconstrues or just manipulates the facts. Water Utility Manager Mark Johnson asked for an opportunity to clear up a few of the more egregious misstatements and offered to answer any questions I had. Below are excerpts from my conversation with Johnson.

What is the La Crosse-La Crescent pipeline?
The pipeline is a pressurized sanitary sewer (forcemain) that is being extended/installed by the city of La Crescent to transport wastewater from La Crescent and discharge it into the city of La Crosse sanitary sewer system. That waste will be treated at La Crosse’s wastewater treatment plant.

What drove the project?

La Crescent’s discharge permit from the Minnesota Pollution Control Agency required them to extend the discharge pipe from their existing wastewater plant to the west channel of the Mississippi River. This requirement led La Crescent to approach La Crosse to discuss and eventually agree on the option of extending the discharge pipe onto Barron Island and then to the La Crosse wastewater plant.

Last we heard crews were tying the La Crescent main into La Crosse’s system. What’s the status? And where does the water main extension from Barron Island stand?

All of the forcemain pipe has been installed, but there are some remaining issues to be addressed before the pipe can be put into service. It was necessary for La Crescent to hire a second contractor to complete the installation of the sewer pipe under the Mississippi River. There is pending litigation in Minnesota Federal Court between La Crescent and the original contractor and its bonding company.

It will be necessary to bid a follow-up project to complete installation of the watermain connecting the municipal water system to Barron Island. Construction on the watermain is anticipated in 2008.

What’s the total price tag? And what’s the cost to La Crosse?

The original project was bid in three sections.

Section A included the sewer forcemain from La Crescent to Barron Island. The bid was $586,071. This cost was 100 percent La Crescent’s.

Section B included the sewer forcemain from Barron Island to La Crosse. The big total for Section B was $369,531. The agreement between the cities split this cost between La Crosse and La Crescent at 15 percent and 85 percent, respectively. Fifteen percent of that total (La Crosse’s share) is about $55,430.

Section C included the watermain connecting Barron Island to La Crosse’s municipal water system. The bid total for section C was $263,674, which is 100 percent La Crosse’s responsibility.

Because the original contractor was unable to install the sewer and water pipes under the Mississippi River, it was necessary for La Crescent to hire a second contractor to complete the forcemain, and it will be necessary to bid a second project to install the watermain connecting the city’s municipal water system to Barron Island. Additional costs related to these two projects will be included in the litigation between La Crescent and the original contractor.

Where are the funds for the Barron Island project coming from?

Sanitary Sewer Utility funds will pay for the cost of the forcemain that La Crosse is responsible for. Water Utility funds will pay for the cost of the watermain.

The city had been waiting for Barron Island redevelopment before extending water. Why do it now?

Having city water available provides added incentive for developers. When the forcemain project was being prepared, it made sense to take advantage of having one contractor install both sewer and water pipes at the same time.

If La Crosse did the watermain extension to Barron Island independent of La Crescent’s project, how much would it likely cost?

An independent project to install the watermain will likely cost more than the original bid.

La Crescent is getting its waste processed. What is La Crosse getting out of the deal?

In January 2007, the La Crosse Common Council approved a 20-year agreement with La Crescent for sewer service. Per the agreement, La Crescent will pay a wholesale rate for wastewater treatment of $1,288 per million gallons. This is consistent with current rates charged to other users — Onalaska, Town of Campbell and Town of Shelby — under contract with La Crosse for wastewater service.

What will be the city’s projected profit each year for processing La Crescent’s waste?

Based on the current average daily flow from La Crescent, annual estimates will be about $125,000.

Samantha Marcus can be reached at (608) 791-8220 or smarcus@lacrossetribune.com.
.
 Advertisement 
 Tell us what you think...

 Comments »

Really wrote on Apr 26, 2008 11:31 PM:

" Again Moderate your thinking is all screwed up. Both are Northsiders, but seperate people. Get a clue. You are a pool of misinformation. "

The Moderate wrote on Apr 26, 2008 6:12 AM:

" I think "just the facts" and "correctanswer" are the same person. "

correctanswer wrote on Apr 23, 2008 10:31 PM:

" I love that this young, intelligent reporter, wet behind the ears can enter our town roughly a year ago and tell us the "truth". The truth about politics, insiders grabbing power and exceptions, and directions that I would bet money on tomorrow that will ultimately transpire. I even wonder if she has met the Royal Family from Ebner Coulee. My oh my. "

just the facts wrote on Apr 23, 2008 3:43 PM:

" Ques:6, If I were to look at the monthly balance sheets ,[ a public document], of the city of LaCrosse starting in April of 2007 and each month thereafter to present; how much total money would have been paid to ,MINNCOM, the contractor from waste water utility and water utility? Whose money was this? How was it accounted for? If these are "MISREADS,MISCONSTRUES,OR MANIPULATIONS, just ask these questions. DO you want the Tribune truth or the whole truth? Oh, never mind I'll go to the next meeting and do it myself! That's the way it has been! "

just the facts wrote on Apr 23, 2008 3:23 PM:

" Samantha,Ques: 3,Why do we need to rebid a follow up project to connect the municipal water system to barron island? It is clearly included in the resolution![$1,219,276.65.] Ques:4, Johnsons math doesn't add up! Our share adds up to $319,104. Wheres the rest of the money going? Ques:5 How can we tax LaCrescent , onalaska, campbell and shelby going forward, for millions of dollars of needed capital improvements to our sewer utility. we have NO taxing authority! As I have pointed out, the ,"Wholesale" rates will barely support the interest on the borrowing, much less the" COST" o treating the sewage! "

just the facts wrote on Apr 23, 2008 2:55 PM:

" Dear Samanta, Public administrators top priority is to perpetuate their jobs! They won't lie to you; they just won't tell you all of the truth! LAX Trib legal notes 6/30/07,resolution to award contract for $1,219,276.65 to extend sewer service from LaCrescent. Ques: 1; Are LAX taxpayers paying for this expense? WHY? Are we financing LaCrescent taxpayers? Ques: 2, Why is LaCrescent paying "wholesale rates", and not retail? Does Johnson know the difference? The interest alone on this amount is 60,000 a year. Who's paying it? This is NOT a good deal. "

correctanswer wrote on Apr 22, 2008 11:19 AM:

" Ms. Marcus- If you expect us to believe that the $586,071 improvement to Barron Island was coincidence you are wrong. Ultimately time will tell if the owner of the 60' of riverfront will control the entire future development with his sidekick. Speaking with past utility workers the present services to that island for the Hotel, etc were not up to code even when installed initially. The previous potential developer did indeed reach an "impasse". I personally believe that it was because the CEO and Czar Kirch said not to eminent domain to the 60'. That was not about to happen to this family of property owners. There is more here than meets the eye at quick glance. "


PLEASE NOTE: Comments on stories that frequently update through the day disappear with each update.
The comments above are from readers. In no way do they represent the views of the La Crosse Tribune.

Click here to report offensive or inappropriate comments. Please identify the comment you're concerned about, the story to which the comment was attached, the date of the comment and the person who made the post.

 Post a comment (150 word limit) »

Log In - If you have already signed up with The LaCrosse Tribune, please sign in now!
Member ID:
*Password:
  Forgot Your Password?
 
Sign Up - To encourage intelligent and meaningful conversation, The LaCrosse Tribune requires all commenters to register before posting comments. It's quick, it's easy, and it's free! Just fill in the information below to get started!

**Your Member ID and password will be required to log in. Your comments will appear under your user name.

Do not use usernames or passwords from your financial accounts!

Note: Fields marked with an asterisk (*) are required!

Create a Member ID:
*Choose a password:
*Re-enter password:
E-mail Address:
Year of Birth:
 

(children under 13 cannot register)

First Name:
Last Name:
Company:
Home Phone:
Business Phone:
Address:
City:
State:
Zip Code:
 

NEWSPAPER ADS

LACROSSE JOBS

TOP HOMES

 
 
Dailies
La Crosse Tribune
Winona Daily News

Weeklies
Coulee News
The Chronicle
Holmen Courier
Houston County News
Onalaska Life
Tomah Journal
Vernon Broadcaster
Westby Times

Regional
Inside Preps
My LIVE! Entertainment
Best of River Valley
Business Report
Healthy Living Today
Strictly Golf
River Valley Bike Trails
River Valley Blogs
River Valley Outdoors

Shoppers
Tri-County Foxxy

Marketplace
Newspaper Ads
Local Website Directory
7 Rivers Rentals
HomeSeller
Wheels Website
Outdoor Motors
Work For You

Portals
La Crosse NET
Winona NET

Classifieds
River Valley Classifieds

Links
Lee Enterprises

About Us | Classifieds | Contact Us | Terms of Use | F.A.Q. | Privacy Policy | Requests | Search | RSS | Videos | Advertiser Directory | Add to My Yahoo!
Copyright © 1997 - 2008 The La Crosse Tribune. All rights reserved.
Material from this site may not be published, broadcast, rewritten or distributed. A Lee Enterprises subsidiary.